"Indefinite Delay" to "Could Be Preserved," the Resurrection of Orange Line to DFW Airport?

On June 22, Dallas Area Rapid Transit's higher-ups sent the bad news: Three projects had been derailed by that $3-billion drop in sales tax receipts: the section of the Orange Line that's supposed to run from Irving to Terminal A at Dallas-Fort Worth International Airport, the Blue Line extension from...
Share this:

On June 22, Dallas Area Rapid Transit's higher-ups sent the bad news: Three projects had been derailed by that $3-billion drop in sales tax receipts: the section of the Orange Line that's supposed to run from Irving to Terminal A at Dallas-Fort Worth International Airport, the Blue Line extension from Ledbetter Station to the UNT Dallas campus and the second downtown Dallas light-rail alignment. "Indefinite delay" was the phrase used. But last night, following a board meeting, DART spokesman Morgan Lyons sent word: The 20-year financial plan under review by the board "will support" the DFW and UNT lines after all ... maybe ... looks like ... fingers crossed. But the D2's still D-layed. Indefinitely.

In a letter DART president Gary Thomas sent to the board last week -- it follows, as does DART's official press release -- he wrote that "a combination of tactics" ("sweeping" $100 mil out of "existing and proposed capital budget projects," using Build America Bonds and finding new revenue streams) will allow for the DFW line to stay on track. The UNT line may stay too, he writes, because, well, since D2's deferred, it's the next logical line following the DFW extension -- but, again, it's a maybe since Thomas is hoping DART can get the State Legislature to move ahead with "the imposition of sales taxes on residential utilities." So, we'll see. He writes:

The projects which are being retained in the funded plan include both the Orange Line light rail expansion to the DFW airport terminals (referred to as I-3) and the South Oak Cliff extension of the Blue Line to the UNT Dallas campus (referred to as SOC-3). Accommodating the inclusion of both of these expansion projects will require a sustained emphasis on revenue enhancement and cost containment. The financial plan assumes agencies that have made financial commitments in support of system additions will make their contributions on a timely basis.
If you're really bored this morning, you can read the entirety of DART's FY 2011 Annual Budget and Twenty-Year Financial Plan right here. But I'd right-click-to-save, because it's ginormous -- 173 pages, each one more riveting than the last. Wait'll you get to the chapter titled "The Lost Decade."

Proposed financial plan supports DART Rail airport connection, South Oak Cliff extension

The final section of the Orange Line light rail project from Belt Line Station at Belt Line and State Highway 161 to Terminal A of DFW International Airport and a Blue Line extension from Ledbetter Station to the UNT Dallas campus could be preserved under a new long-range financial plan being reviewed by the DART Board of Directors. DART staff briefed the Board of Directors on the plan during their August 10 Board meeting.

The Board voted to send a draft Fiscal Year 2011 budget and updated 20-Year Financial Plan to the cities within the DART Service Area for review. The cities do not approve the budget, but are given at least 30 days to review it. The proposed FY 2011 budget is $1.25 billion dollars and includes budgets for operations ($422 million), capital ($689.3 million) and debt service ($139.4 million). Board members are scheduled to approve the budget and financial plan on September 28.

The rail expansion projects would be funded through a mix of project cost savings, increased debt and, if approved, additional federal funds. The Orange Line extension, I-3, would likely be finished in 2014, one year beyond the planned completion of 2013. The first two sections of the Orange Line, which begin at the Bachman Station in northwest Dallas, are scheduled to open in 2012. The three-mile Blue Line extension, SOC-3, would be completed in 2019.

Since announcing a projected shortfall in long-term sales tax revenues earlier this year, agency officials have been reviewing funding strategies for capital projects scheduled beyond the current 37-mile light rail expansion, including the second Downtown Dallas alignment. The adjustment in DART Rail operating headways from 10 to 15 minutes lessens the need to construct the alignment for an extended period. There are also new considerations with the potential inclusion of new streetcar lines in the Central Business District and to Oak Cliff. Although the draft financial plan does not include funding for the second downtown alignment, staff will continue planning for the line taking these new initiatives into account, including the pursuit of federal funding.

The completion of the Green Line from Pleasant Grove to Carrollton and the new Lake Highlands Station in December; the Blue Line extension from Garland to Rowlett and the first two sections of the Orange Line from Bachman Station in Northwest Dallas to Irving in 2012, are not affected by the projected shortfall. The proposed 20-year financial plan includes $4.7 billion in capital project funds for the rail expansion and other projects such as the planned purchase of new buses and other items required to maintain the agency's state of good repair.

"We said we would work hard to solve the funding problem of the Orange Line and all of our major capital projects and we believe we have taken significant steps toward that goal," DART President/Executive Director Gary Thomas said. Thomas said the agency will continue its review of funding alternatives for other planned projects not already under contract. There is no timeline for completing the review.

In March, DART reported long-term (for fiscal years 2012 and beyond) projections of lower than expected sales tax receipts. In addition to requiring adjustments in current service levels the sales tax projections will also have a significant impact on the ability of the agency to undertake future expansion projects. Updated 20-year sales tax projections show DART receiving approximately $3 billion less in sales tax income than the amount projected as recently as May 2009. However, all estimates confirm DART will be able to continue the routine replacement of fleet vehicles and maintain a state of good repair for its current facilities and those under construction.

More than 75% of the agency's income is from the collection of the one-percent sales tax in each of the 13 cities served by DART. Anticipated sales tax receipts for fiscal year 2010 are expected to be between $12 and $14 million below the original estimate of $387.8 million.

Presidents Letter to the Board

KEEP THE OBSERVER FREE... Since we started the Dallas Observer, it has been defined as the free, independent voice of Dallas, and we'd like to keep it that way. Your membership allows us to continue offering readers access to our incisive coverage of local news, food, and culture with no paywalls. You can support us by joining as a member for as little as $1.